Skip to Main Content

I-5 NCEP Weekly Look-Ahead: November 20 to 26, 2023

I-5 NCEP Weekly Look-Ahead: November 20 to 26, 2023
17 Nov 2023 by Metro

Construction Update Community Meeting: Save the Date   
Join Metro’s I-5 North County Enhancements Project for the next community meeting to receive updates on the construction activities along the I-5 freeway. 
 
Project staff will outline upcoming construction timelines and provide an update on activities in the Santa Clarita Valley and North LA County communities, including a recap of the demolition of the Weldon Canyon Rd bridge, and activities planned for Stage 2 of the project. We look forward to hearing your questions, comments, and to keeping you informed for the duration of construction. | More Information
 
Wednesday, November 29, 2023, 6PM to 7:30PM 
Zoom Link: us02web.zoom.us/j/99714777647 
Webinar ID: 997 1477 7647 
Call-in: (213) 338-8477 
 
Special accommodations are available to the public for Metro-sponsored meetings. All requests for reasonable accommodations and translation must be made at least three working days (72 hours) in advance of the scheduled meeting date.


NOTE: I-5 restriping between SR-14 to Calgrove Bl taking place Monday, 11/20 and Tuesday, 11/21. Prepare for lane reductions in both northbound and southbound directions. Freeway closures are paused from Wednesday, 11/22 to Monday, 11/27 due to Thanksgiving.

Prepare for weeknight intermittent lane reductions in both directions between SR-14 and Parker Rd from 8pm to 6am to support all the below activities on I-5. Crews begin mobilizing at 6am and work hours are 7am to 4pm and 7pm to 6am on weekdays, and Saturdays as needed. 

SR-14 to Magic Mountain Pkwy

Gavin Canyon Undercrossing bridge construction. Prepare for intermittent full lane closures of The Old Rd between Weldon Canyon Rd and Calgrove Bl, Monday through Friday from 9pm to 5am. View full notice for detour routes. | Full Notice  

Calgrove Bl Undercrossing bridge falsework installation.  Prepare for intermittent full lane closures of Calgrove Bl between The Old Rd and Wiley Canyon Rd, Monday through Friday from 9pm to 6am. View full notice for detour routes. | Full Notice

Southbound outside shoulder retaining wall excavation and drainage system work between Weldon Canyon Rd and Calgrove Bl. View full notice for schedule and detour routes. | Full Notice

Center median retaining wall construction and drainage system work between SR-14 and Magic Mountain Pkwy. | Full Notice

SR-14 to Magic Mountain Pkwy

Santa Clara Overhead bridge forming, rebar installation, concrete placement and fine grading activity between Magic Mountain Pkwy and Rye Canyon Rd. | Full Notice

Castaic Creek bridge forming, rebar installation, and concrete placement between Biscailuz Dr and Hasley Canyon Rd. | Full Notice

Center median concrete placement and pipe replacement between Magic Mountain Pkwy Rd and Parker Rd. | Full Notice

Essential Details

  • Work hours: Monday through Friday and Saturday, as needed from 7am to 4pm and 7pm to 6am. Crews will begin to mobilize at 6am.
  • No two consecutive ramps in the same direction will be closed at the same time. Detours to the next on-ramp will be posted for each closure.
  • Traffic will be maintained in each direction.
  • All lanes will reopen by 6am each morning.
  • No lane closures will be implemented during morning or evening peak traffic hours.
  • The speed limit in construction work zones is reduced to 55 miles per hour.

Noteworthy

Access to emergency responders will be maintained. Construction is a dynamic process, it is subject to weather conditions, and information is subject to change, visit the project website for the most up to date information and a weekly listing.