  • 28 Apr 2023 by Metro

     

    Prepare for weeknight intermittent lane reductions in both directions between SR-14 and Parker Rd from 8pm to 6am to support all the below activities on I-5. Crews begin mobilizing at 6am and work hours are 7am to 4pm and 7pm to 6am on weekdays, and Saturdays as needed. 

    SR-14 to Magic Mountain Pkwy 
    Weldon Canyon Rd bridge deck and rebar work. One-way traffic control with a flagger will be used as needed Monday through Friday at Weldon Canyon Rd/Coltrane Av. | More Information 

    Southbound outside shoulder excavation, shoring and retaining wall work between Weldon Canyon Overcrossing and Calgrove Bl. Prepare for intermittent closures of southbound Calgrove Bl on- and off-ramps Monday through Friday from 7pm to 6am. Signage is posted along the detour routes and at the preceding off-ramp. Flagger controlled construction access from The Old Road at Gavin Canyon Undercrossing may be utilized. | More Information 

    • Southbound on-ramp detours:   
      • Westbound Calgrove Bl: Right on The Old Road, merge onto San Fernando Rd, right on Sepulveda Bl, merge onto Roxford St, enter southbound I-5 at Sepulveda Bl/Roxford St on-ramp  
      • Eastbound Calgrove Bl: Enter northbound I-5 Calgrove Bl on-ramp, exit northbound Lyons Av/Pico Canyon Rd off-ramp, right on Lyons Av, enter southbound I-5 at Lyons Av on-ramp  

    Electrical work for conduit installation at McBean Pkwy and Valencia Bl on- and off-ramps. Prepare for the following closures anticipated Monday, May 1 through Friday, May 5 from 7pm to 5am. Detour signage is placed at the preceding off-ramp indicating the closure | More Information 

    • Nightly closures of the southbound McBean Pkwy off-ramp. Vehicles will be detoured to the preceding off-ramp at Valencia Bl.   
    • Nightly closures of the southbound Valencia Bl on-ramp 
      • Detour: Continue southbound on The Old Road, turn left on McBean Pkwy, continue to the southbound I-5 McBean Pkwy on-ramp
    • Nightly closures of the northbound Valencia Bl on-and-off ramp 
      • Detour: Vehicles will be detoured to the preceding off-ramp at McBean Pkwy. 
      • Detour: Continue northbound on The Old Road, turn right on Magic Mountain Pkwy, left onto the northbound I-5 Magic Mountain Pkwy on-ramp. 

    Gavin Canyon Undercrossing bridge foundation work along the northbound I-5 shoulder between Calgrove Bl and Weldon Canyon Rd. Activities include steel rebar, forming, pour, and utility work. Construction access from The Old Road may be utilized. | More Information 

    Center median retaining wall construction. Activities include excavation, backfill, shoring, form, and concrete placement between SR-14 and Magic Mountain Pkwy. | More Information 

    Outside shoulder excavation and shoring work in both directions between Weldon Canyon bridge and Calgrove Bl. Equipment includes a directional drilling machine, usage of trucks, forklifts, and concrete mixing support. | More Information  

    Butte Canyon bridge deck work in the center median between Pico Canyon Rd/Lyons Av and McBean Pkwy, adjacent to Vista Valencia Golf Course, anticipated Monday, May 1 through Wednesday, May 3. | More Information 

    Magic Mountain Pkwy to Parker Rd  
    Full closure of Rye Canyon Rd between The Old Road and Avenue Stanford for crane relocation and excavation, anticipated anticipated Monday, May 1 and Thursday, May 4 from 7pm to 5am. Contingency dates will be used, only if needed on Tuesday, May 2 and Friday, May 5 from 7pm to 5am. | More Information

    • Detour 1: Traveling northbound on The Old Road, turn left on Henry Mayo Dr, enter eastbound SR-126/Newhall Ranch Rd, continue on Newhall Ranch Rd to Rye Canyon Rd 
    • Detour 2: Traveling southbound on The Old Road, turn left on Magic Mountain Pkwy, left on McBean Pkwy, left on Newhall Ranch Rd, continue Newhall Ranch Rd to Rye Canyon Rd 
    • Detour 3: Traveling westbound on Rye Canyon Rd, turn left on Newhall Ranch Rd, right on McBean Pkwy, right on Magic Mountain Pkwy, continue to The Old Road/Rye Canyon Rd

    Rye Canyon Rd bridge pile driving between The Old Road and Avenue Stanford. Prepare for lane closures on westbound Rye Canyon Rd between Avenue Stanford and The Old Road, anticipated Monday, May 1 through Saturday, May 6 from 6am to 4pm. | More Information

    Castaic Creek bridge deck concrete placement and backwall construction in the center median between SR-126 and Hasley Canyon Rd anticipated Monday, May 1 through Saturday, May 6 from 8pm to 6am. | More Information 

    Center median roadway base activity between Magic Mountain Pkwy and SR-126. | More Information  

    Upcoming in May
    Falsework removal for the construction of the new Weldon Canyon Rd Bridge will require multiple weeknight directional closures between SR-14 and Calgrove Bl from 10pm to 4am. Primary detour routes will include the SR-14, Newhall Ranch Rd, and Golden Valley Rd. Local access will be available at the I-5 ramp between Calgrove Bl and Newhall Ranch Rd. | More Information  

    • Northbound I-5 directional closures   
      • Monday, May 22 from 10pm to 4am
      • Tuesday, May 23 from 10pm to 4am   
      • Wednesday, May 24 from 10pm to 4am  
    • Southbound I-5 directional closures
      • ​​​​Tuesday, May 30 from 10pm-4am
      • Wednesday, May 31 from 10pm-4am
      • Thursday, June 1 from 10pm to 4pm  
    • Northbound/Southbound directional closure contingency date: Thursday, May 25 from 10pm to 4am, if needed 

    Essential Details    

    • Work hours: Monday through Friday and Saturday, as needed from 7am to 4pm and 7pm to 6am. Crews will begin to mobilize at 6am.    
    • No two consecutive ramps in the same direction will be closed at the same time. Detours to the next on-ramp will be posted for each closure. 
    • Traffic will be maintained in each direction. 
    • All lanes will be reopened by 6am each morning.
    • No lane closures will be implemented during morning or evening peak traffic hours.
    • The speed limit in construction work zones is reduced to 55-miles per hour.    

    Noteworthy
    Access to emergency responders will be maintained. Construction is a dynamic process, it is subject to weather conditions, and information is subject to change, visit the project website for the most up to date information and a weekly listing.   

  • 27 Apr 2023 by City of Santa Clarita

    GEAR UP FOR THE 44TH ANNUAL SANTA CLARITA DODGER DAY!

    Watch the Dodgers Take on the Giants on June 17

    “It’s Time for Dodger Baseball!” America’s favorite pastime is in full swing and so is Santa Clarita Dodger Day! The City of Santa Clarita is excited to invite residents to purchase tickets for the 44th Annual City of Santa Clarita Dodger Day. This year’s game will be between the hometown Los Angeles Dodgers and their longtime rivals, the San Francisco Giants at Dodger Stadium on Saturday, June 17, at 6:10 p.m. Tickets are on sale now and can be purchased online by visiting SCVDodgerDay.com.

    Dodger Day, sponsored by Henry Rodriguez, State Farm Insurance Agent, offers Santa Clarita residents a chance to catch a ballgame with family and friends. Ticket prices range from $60 each for Reserve Value MVP to $99 Infield Loge Box seats. A limited amount of tickets will be available in various seating tiers and tickets are grouped together, ensuring attendees will sit near other Santa Clarita residents during the game. The first 500 tickets sold will receive a Santa Clarita Dodger Day t-shirt to commemorate the event. For more information, please visit SCVDodgerDay.com or contact Ashley Gurrola at (661) 286-4165.

  • 21 Apr 2023 by Metro


    Prepare for weeknight intermittent lane reductions in both directions between SR-14 and Parker Rd from 8pm to 6am to support all the below activities on I-5. Crews begin mobilizing at 6am and work hours are 7am to 4pm and 7pm to 6am on weekdays, and Saturdays as needed. 

    SR-14 to Magic Mountain Pkwy 
    Weldon Canyon Rd bridge deck and rebar work. One-way traffic control with a flagger will be used as needed Monday through Friday at Weldon Canyon Rd/Coltrane Av. | More Information 

    Southbound outside shoulder excavation, shoring and retaining wall work between Weldon Canyon Overcrossing and Calgrove Bl. Prepare for intermittent closures of southbound Calgrove Bl on- and off-ramps Monday through Friday from 7pm to 6am. Signage is posted along the detour routes and at the preceding off-ramp. Flagger controlled construction access from The Old Road at Gavin Canyon Undercrossing may be utilized. | More Information 

    • Southbound on-ramp detours:   
    • Westbound Calgrove Bl: Right on The Old Road, merge onto San Fernando Rd, right on Sepulveda Bl, merge onto Roxford St, enter southbound I-5 at Sepulveda Bl/Roxford St on-ramp  
    • Eastbound Calgrove Bl: Enter northbound I-5 Calgrove Bl on-ramp, exit northbound Lyons Av/Pico Canyon Rd off-ramp, right on Lyons Av, enter southbound I-5 at Lyons Av on-ramp  

    Electrical work for conduit installation at the southbound McBean Pkwy off-ramp, and northbound McBean Pkwy on-ramp. Prepare for nightly ramp closures on Monday, April 24 through Wednesday, April 26 from 7pm to 5am. | More Information 

    • Nightly closures of the southbound McBean Pkwy off-ramp. Detour signage is placed at the preceding off-ramp indicating the closure.   
    • Nightly closures of the northbound McBean Pkwy on-ramp 
    • Detour: Continue on McBean Pkwy to The Old Road, turn right on Valencia Bl, continue to the northbound I-5 Valencia Bl on-ramp.  

    Gavin Canyon Undercrossing bridge foundation work along the northbound I-5 shoulder between Calgrove Bl and Weldon Canyon Rd. Activities include steel rebar, forming and utility work. Construction access from The Old Road may be utilized. | More Information 

    Center median retaining wall construction and concrete barrier work.  Activities include excavation, backfill, shoring, form, and concrete work between SR-14 and Magic Mountain Pkwy. | More Information 

    Outside shoulder excavation and shoring work in both directions between Weldon Canyon bridge and Calgrove Bl. Equipment includes a directional drilling machine, usage of trucks, forklifts, and concrete mixing support. | More Information  

    Butte Canyon bridge deck concrete placement in the center median between Pico Canyon Rd/Lyons Av and McBean Pkwy, adjacent to Vista Valencia Golf Course, anticipated on Tuesday, April 25 from 8pm to 6am. | More Information 

    Magic Mountain Pkwy to Parker Rd  
    Full closure of Rye Canyon Rd between The Old Road and Avenue Stanford for crane relocation, anticipated Thursday, April 27 from 7pm to 5am and Friday, April 28 from 7pm to 5am as a contingency date only if needed. | More Information 

    • Detour 1: Traveling northbound on The Old Road, turn left on Henry Mayo Dr, enter eastbound SR-126/Newhall Ranch Rd, continue on Newhall Ranch Rd to Rye Canyon Rd  
    • Detour 2: Traveling southbound on The Old Road, turn left on Magic Mountain Pkwy, left on McBean Pkwy, left on Newhall Ranch Rd, continue Newhall Ranch Rd to Rye Canyon Rd  
    • Detour 3: Traveling westbound on Rye Canyon Rd, turn left on Newhall Ranch Rd, right on McBean Pkwy, right on Magic Mountain Pkwy, continue to The Old Road/Rye Canyon Rd 

    Rye Canyon Rd bridge pile driving between The Old Road and Avenue Stanford. Prepare for lane closures on westbound Rye Canyon Rd between Avenue Stanford and The Old Road, anticipated on Monday, April 24 through Thursday, April 27 from 6am to 4pm. | More Information 

    Castaic Creek bridge deck concrete placement in the center median between SR-126 and Hasley Canyon Rd. | More Information 

    Center median roadway base, paving, and concrete removal activity between Magic Mountain Pkwy and SR-126. | More Information   

    ________________________________________________

    Essential Details    

    • Work hours: Monday through Friday and Saturday, as needed from 7am to 4pm and 7pm to 6am. Crews will begin to mobilize at 6am.    
    • No two consecutive ramps in the same direction will be closed at the same time. Detours to the next on-ramp will be posted for each closure. 
    • Traffic will be maintained in each direction. 
    • All lanes will be reopened by 6am each morning.
    • No lane closures will be implemented during morning or evening peak traffic hours.
    • The speed limit in construction work zones is reduced to 55-miles per hour.    

    Noteworthy
    Access to emergency responders will be maintained. Construction is a dynamic process, it is subject to weather conditions, and information is subject to change, visit the project website for the most up to date information and a weekly listing.   

  •  

     

    The Santa Clarita Valley Historical Society is pleased to announce that it has been selected to participate in the American Alliance of Museums’ 2023 Museum Assessment Program, a critical step toward museum accreditation. AAM, founded in 1906, is a national organization representing the entire scope of the museum field.

    Since 1975, the SCV Historical Society has been a resource for the valley and surrounding areas of local history, preserving artifacts, and sharing the stories of the people who founded and grew the communities of Newhall, Saugus, Canyon Country and Valencia into the city of Santa Clarita and beyond.

    “It’s a great honor for the Historical Society to have been chosen for the Museum Assessment Program,” said Society president Alan Pollack. “This reflects our determination to evolve from a small, volunteer-driven local history advocate to a full, professional museum presence in Santa Clarita. We intend to create one of the premier local history museums in Southern California.”

    For over 50 years, the Museum Assessment Program (MAP) has helped more than 5,000 museums of all types strengthen their operations, plan for the future, and meet current professional standards. “We served a relatively small, incorporated town of about 70,000 people when we opened in 1980 with one museum building in Hart Park,” said Society vice president Leon Worden. “Today, we need to be serving a community that is not only four or five times larger but also more sophisticated and diverse with higher expectations for a museum experience. Staff archivist Eva Gritz is a key member of the Historical Society’s MAP team.

    “We assembled a high-powered steering committee of local community leaders last year and retained a professional museum consultant to help us plan a new museum in one of our eight buildings, and you will be hearing more about it in the months ahead,” Worden said. “In the meantime, we’ve been doing the work behind the scenes that the public doesn’t necessarily see. We’ve started to ramp up staffing, and we are implementing ‘best practices’ in collections care to curate a massive collection of artifacts and photographs. We expect the MAP assessment to serve as both a checkup to ensure we’re on the right track and a roadmap for further improvements as we pursue accreditation in our field.”

    Conducted over the course of a year, MAP assessments help museums look at both functional and strategic aspects of their operations; examine diversity, equity, access, and inclusion issues as they relate to the assessment focus; and include a peer-reviewed site visit.

    About the Santa Clarita Valley Historical Society:

    The mission of the Santa Clarita Valley Historical Society is to stimulate public interest in the history of the area, to collect and preserve facts, artifacts, and historical structures pertinent to the area, and to educate and inform the public. The Society is headquartered in the Santa Clarita History Center at Hart Park in Newhall, and Society members are involved in outreach efforts throughout the community. For more information, visit www.scvhs.org.

    About the American Alliance of Museums:

    The American Alliance of Museums is the only organization representing the entire museum field, from art and history museums to science centers and zoos. Since 1906, AAM has been championing museums through advocacy and providing museum professionals with the resources, knowledge, inspiration, and connections they need to move the field forward. For more information on the American Alliance of Museums, and the impact of museums, visit aam-us.org.

  •  

     

     

    EV Programs and Incentives

     

    With gas prices likely rising this summer, have you considered an electric vehicle (EV)? Charging an EV during off-peak hours costs less than half the price of fueling with gasoline. There are many different EV makes and models to choose from now, with exciting designs and options. Rebates and other incentives can make EVs even more affordable. You can help people in your community realize the benefits of driving electric by sharing helpful information from the toolkit below.

     

    This is our first monthly “EV toolkit,” which focuses on programs and incentives to help lower the price of an EV. These toolkits will bring together a variety of EV information in one place: a news article, a few social media recommendations, key web links, images, and other helpful EV tools and resources.

     

    We plan to share toolkits with you on a variety of EV themes. We hope you enjoy the consolidated information and will share with your constituents and/or others in your community. 

     

    Download Toolkit

     

    Facebook Twitter

  • 14 Apr 2023 by Metro


    Prepare for weeknight intermittent lane reductions in both directions between SR-14 and Parker Rd from 8pm to 6am to support all the below activities on I-5. Crews begin mobilizing at 6am and work hours are 7am to 4pm and 7pm to 6am on weekdays, and Saturdays as needed. 

    SR-14 to Magic Mountain Pkwy 
    Weldon Canyon Rd bridge deck work. One-way traffic control with a flagger will be used as needed Monday through Friday at Weldon Canyon Rd/Coltrane Av. | More Information 

    Southbound outside shoulder excavation, shoring and retaining wall work between Weldon Canyon Overcrossing and Calgrove Bl. Prepare for intermittent closures of southbound Calgrove Bl on- and off-ramps Monday through Friday from 7pm to 6am. Signage is posted along the detour routes and at the preceding off-ramp. Flagger controlled construction access from The Old Road at Gavin Canyon Undercrossing may be utilized. | More Information 

    • Southbound on-ramp detours:   
    • Westbound Calgrove Bl: Right on The Old Road, merge onto San Fernando Rd, right on Sepulveda Bl, merge onto Roxford St, enter southbound I-5 at Sepulveda Bl/Roxford St on-ramp  
    • Eastbound Calgrove Bl: Enter northbound I-5 Calgrove Bl on-ramp, exit northbound Lyons Av/Pico Canyon Rd off-ramp, right on Lyons Av, enter southbound I-5 at Lyons Av on-ramp  

    Gavin Canyon Undercrossing bridge foundation work along the northbound I-5 shoulder between Calgrove Bl and Weldon Canyon Rd. Activities include steel rebar, forming and utility work. Construction access from The Old Road may be utilized. | More Information 

    Center median retaining wall construction and concrete barrier work.  Activities include excavation, backfill, shoring, form, and concrete work between SR-14 and Magic Mountain Pkwy. | More Information  

    Outside shoulder excavation and shoring work in both directions between Weldon Canyon bridge and Calgrove Bl. Equipment includes a directional drilling machine, usage of trucks, forklifts, and concrete mixing support. | More Information  

    Butte Canyon bridge deck work (rebar installation) in the center median between Pico Canyon Rd/Lyons Av and McBean Pkwy, adjacent to Vista Valencia Golf Course. | More Information 

    Magic Mountain Pkwy to Parker Rd  
    Full closure of Rye Canyon Rd between The Old Road and Avenue Stanford for crane assembly adjacent to the I-5 bridge, anticipated Wednesday, April 19 from 7pm to 5am and Thursday, April 20 from 7pm to 5am as a contingency date only if needed. 

    • Detour 1: Traveling northbound on The Old Road, turn left on Henry Mayo Dr, enter eastbound SR-126/Newhall Ranch Rd, continue on Newhall Ranch Rd to Rye Canyon Rd  
    • Detour 2: Traveling southbound on The Old Road, turn left on Magic Mountain Pkwy, left on McBean Pkwy, left on Newhall Ranch Rd, continue Newhall Ranch Rd to Rye Canyon Rd  
    • Detour 3: Traveling westbound on Rye Canyon Rd, turn left on Newhall Ranch Rd, right on McBean Pkwy, right on Magic Mountain Pkwy, continue to The Old Road/Rye Canyon Rd 

    Rye Canyon Rd bridge crane maintenance work and pile driving between The Old Road and Avenue Stanford. Prepare for lane closures on westbound Rye Canyon Rd between Avenue Stanford and The Old Road, anticipated from Monday, April 17 through Friday April 21 from 6am to 4pm. | More Information 

    Castaic Creek bridge deck work (rebar installation) in the center median between SR-126 and Hasley Canyon Rd. | More Information 

    Southbound outside shoulder electrical work at the SR-126 on-ramp. Prepare for nighttime closures of the southbound I-5 to SR-126 on-ramp, anticipated Monday, April 17 through Tuesday, April 18 from 9pm to 5am.| More Information 

    • Detour: Continue on SR-126 to Henry Mayo Dr, turn right on The Old Road, left onto The Old Road/Rye Canyon Rd southbound I-5 on-ramp.  

    Center median roadway base, paving, and concrete removal activity between Magic Mountain Pkwy and SR-126. | More Information   

    ________________________________________________

    Essential Details    

    • Work hours: Monday through Friday and Saturday, as needed from 7am to 4pm and 7pm to 6am. Crews will begin to mobilize at 6am.    
    • No two consecutive ramps in the same direction will not be closed at the same time. Detours to the next on-ramp will be posted for each closure. 
    • Traffic will be maintained in each direction. 
    • All lanes will be reopened by 6am each morning.
    • No lane closures will be implemented during morning or evening peak traffic hours.
    • The speed limit in construction work zones is reduced to 55-miles per hour.    

    Noteworthy
    Access to emergency responders will be maintained. Construction is a dynamic process, it is subject to weather conditions, and information is subject to change, visit the project website for the most up to date information and a weekly listing.   

  • 07 Apr 2023 by Metro

     

     

     

    Prepare for weeknight intermittent lane reductions in both directions between SR-14 and Parker Rd from 8pm to 6am to support all the below activities on I-5. Crews begin mobilizing at 6am and work hours are 7am to 4pm and 7pm to 6am on weekdays, and Saturdays as needed. 

    SR-14 to Magic Mountain Pkwy 
    Weldon Canyon Rd bridge deck work. One-way traffic control with a flagger will be used as needed Monday through Friday at Weldon Canyon Rd/Coltrane Av. | More Information 

    Southbound outside shoulder excavation, shoring and retaining wall work between Weldon Canyon Overcrossing and Calgrove Bl. Prepare for intermittent closures of southbound Calgrove Bl on- and off-ramps from 7pm to 6am. Signage is posted along the detour routes and at the preceding off-ramp. Flagger controlled construction access from The Old Road at Gavin Canyon Undercrossing may be utilized. | More Information 

    • Southbound on-ramp detours:   
    • Westbound Calgrove Bl: Right on The Old Road, merge onto San Fernando Rd, right on Sepulveda Bl, merge onto Roxford St, enter southbound I-5 at Sepulveda Bl/Roxford St on-ramp  
    • Eastbound Calgrove Bl: Enter northbound I-5 Calgrove Bl on-ramp, exit northbound Lyons Av/Pico Canyon Rd off-ramp, right on Lyons Av, enter southbound I-5 at Lyons Av on-ramp  

    Center median retaining wall construction and concrete barrier work.  Activities include excavation, backfill, shoring, form, and concrete work between SR-14 and Magic Mountain Pkwy. | More Information 

    Outside shoulder excavation and shoring work in both directions between Weldon Canyon bridge and Calgrove Bl. Equipment includes a directional drilling machine, usage of trucks, forklifts, and concrete mixing support. | More Information  

    Butte Canyon bridge deck rebar work (rebar installation) in the center median between Pico Canyon Rd/Lyons Av and McBean Pkwy, adjacent to Vista Valencia Golf Course. | More Information 

    Magic Mountain Pkwy to Parker Rd  
    Pile driving adjacent to the I-5 bridge at Rye Canyon Rd between The Old Road and Avenue Stanford. Prepare for lane closures on westbound Rye Canyon Rd between Avenue Stanford and The Old Road, anticipated Monday, April 10 through Friday, April 14 from 6am to 4pm. | More Information 

    Castaic Creek bridge deck work (rebar installation) in the center median between SR-126 and Hasley Canyon Rd. | More Information 

    Electrical work at southbound SR-126 and Parker Rd. Prepare for nighttime closures of the southbound I-5 to SR-126 off-ramp, anticipated Monday, April 10 through Thursday, April 13 from 9pm to 5am.| More Information 

    • Detour: From southbound I-5, exit Magic Mountain Pkwy, reenter northbound I-5 at Magic Mountain Pkwy, continue on northbound I-5 to SR-126.  

    Sound wall foundation construction along southbound outside shoulder and The Old Road between Villa Canyon Rd and Hasley Canyon Rd. Activities include excavation, auger drilling, setting of steel rebar, concrete work, and material handling. Construction access from The Old Road may be utilized. | More Information 

    Center median roadway base, paving, and concrete removal activity between Magic Mountain Pkwy and SR-126. | More Information   

    ________________________________________________

    Essential Details    

    • Work hours: Monday through Friday and Saturday, as needed from 7am to 4pm and 7pm to 6am. Crews will begin to mobilize at 6am.    
    • No two consecutive ramps in the same direction will not be closed at the same time. Detours to the next on-ramp will be posted for each closure. 
    • Traffic will be maintained in each direction. 
    • All lanes will be reopened by 6am each morning.
    • No lane closures will be implemented during morning or evening peak traffic hours.
    • The speed limit in construction work zones is reduced to 55-miles per hour.    

    Noteworthy
    Access to emergency responders will be maintained. Construction is a dynamic process, it is subject to weather conditions, and information is subject to change, visit the project website for the most up to date information and a weekly listing.