I-5 NCEP Weekly Look-Ahead: April 24 to April 30, 2023

I-5 NCEP Weekly Look-Ahead: April 24 to April 30, 2023
21 Apr 2023 by Metro


Prepare for weeknight intermittent lane reductions in both directions between SR-14 and Parker Rd from 8pm to 6am to support all the below activities on I-5. Crews begin mobilizing at 6am and work hours are 7am to 4pm and 7pm to 6am on weekdays, and Saturdays as needed. 

SR-14 to Magic Mountain Pkwy 
Weldon Canyon Rd bridge deck and rebar work. One-way traffic control with a flagger will be used as needed Monday through Friday at Weldon Canyon Rd/Coltrane Av. | More Information 

Southbound outside shoulder excavation, shoring and retaining wall work between Weldon Canyon Overcrossing and Calgrove Bl. Prepare for intermittent closures of southbound Calgrove Bl on- and off-ramps Monday through Friday from 7pm to 6am. Signage is posted along the detour routes and at the preceding off-ramp. Flagger controlled construction access from The Old Road at Gavin Canyon Undercrossing may be utilized. | More Information 

  • Southbound on-ramp detours:   
  • Westbound Calgrove Bl: Right on The Old Road, merge onto San Fernando Rd, right on Sepulveda Bl, merge onto Roxford St, enter southbound I-5 at Sepulveda Bl/Roxford St on-ramp  
  • Eastbound Calgrove Bl: Enter northbound I-5 Calgrove Bl on-ramp, exit northbound Lyons Av/Pico Canyon Rd off-ramp, right on Lyons Av, enter southbound I-5 at Lyons Av on-ramp  

Electrical work for conduit installation at the southbound McBean Pkwy off-ramp, and northbound McBean Pkwy on-ramp. Prepare for nightly ramp closures on Monday, April 24 through Wednesday, April 26 from 7pm to 5am. | More Information 

  • Nightly closures of the southbound McBean Pkwy off-ramp. Detour signage is placed at the preceding off-ramp indicating the closure.   
  • Nightly closures of the northbound McBean Pkwy on-ramp 
  • Detour: Continue on McBean Pkwy to The Old Road, turn right on Valencia Bl, continue to the northbound I-5 Valencia Bl on-ramp.  

Gavin Canyon Undercrossing bridge foundation work along the northbound I-5 shoulder between Calgrove Bl and Weldon Canyon Rd. Activities include steel rebar, forming and utility work. Construction access from The Old Road may be utilized. | More Information 

Center median retaining wall construction and concrete barrier work.  Activities include excavation, backfill, shoring, form, and concrete work between SR-14 and Magic Mountain Pkwy. | More Information 

Outside shoulder excavation and shoring work in both directions between Weldon Canyon bridge and Calgrove Bl. Equipment includes a directional drilling machine, usage of trucks, forklifts, and concrete mixing support. | More Information  

Butte Canyon bridge deck concrete placement in the center median between Pico Canyon Rd/Lyons Av and McBean Pkwy, adjacent to Vista Valencia Golf Course, anticipated on Tuesday, April 25 from 8pm to 6am. | More Information 

Magic Mountain Pkwy to Parker Rd  
Full closure of Rye Canyon Rd between The Old Road and Avenue Stanford for crane relocation, anticipated Thursday, April 27 from 7pm to 5am and Friday, April 28 from 7pm to 5am as a contingency date only if needed. | More Information 

  • Detour 1: Traveling northbound on The Old Road, turn left on Henry Mayo Dr, enter eastbound SR-126/Newhall Ranch Rd, continue on Newhall Ranch Rd to Rye Canyon Rd  
  • Detour 2: Traveling southbound on The Old Road, turn left on Magic Mountain Pkwy, left on McBean Pkwy, left on Newhall Ranch Rd, continue Newhall Ranch Rd to Rye Canyon Rd  
  • Detour 3: Traveling westbound on Rye Canyon Rd, turn left on Newhall Ranch Rd, right on McBean Pkwy, right on Magic Mountain Pkwy, continue to The Old Road/Rye Canyon Rd 

Rye Canyon Rd bridge pile driving between The Old Road and Avenue Stanford. Prepare for lane closures on westbound Rye Canyon Rd between Avenue Stanford and The Old Road, anticipated on Monday, April 24 through Thursday, April 27 from 6am to 4pm. | More Information 

Castaic Creek bridge deck concrete placement in the center median between SR-126 and Hasley Canyon Rd. | More Information 

Center median roadway base, paving, and concrete removal activity between Magic Mountain Pkwy and SR-126. | More Information   

________________________________________________

Essential Details    

  • Work hours: Monday through Friday and Saturday, as needed from 7am to 4pm and 7pm to 6am. Crews will begin to mobilize at 6am.    
  • No two consecutive ramps in the same direction will be closed at the same time. Detours to the next on-ramp will be posted for each closure. 
  • Traffic will be maintained in each direction. 
  • All lanes will be reopened by 6am each morning.
  • No lane closures will be implemented during morning or evening peak traffic hours.
  • The speed limit in construction work zones is reduced to 55-miles per hour.    

Noteworthy
Access to emergency responders will be maintained. Construction is a dynamic process, it is subject to weather conditions, and information is subject to change, visit the project website for the most up to date information and a weekly listing.