Skip to Main Content

I-5 NCEP Weekly Look-Ahead June 18 to June 25, 2023

I-5 NCEP Weekly Look-Ahead June 18 to June 25, 2023
16 Jun 2023 by Metro


Prepare for weeknight intermittent lane reductions in both directions between SR-14 and Parker Rd from 8pm to 6am to support all the below activities on I-5. Crews begin mobilizing at 6am and work hours are 7am to 4pm and 7pm to 6am on weekdays, and Saturdays as needed. 


SR-14 to Magic Mountain Pkwy 

Weldon Canyon Rd bridge construction. One-way traffic control with a flagger will be used as needed at Weldon Canyon Rd and Coltrane Av. | Full Notice 
 

Southbound outside shoulder excavation, shoring, and retaining wall work between Weldon Canyon Overcrossing and Magic Mountain Pkwy. | Full Notice 


Electrical work in the center median, southbound Magic Mountain Pkwy on-ramp, northbound Magic Mountain Pkwy off-ramp, and southbound Valenica Bl off-ramp. View the full construction notice for the schedule and detour routes. | Full Notice  


Center median retaining wall construction between SR-14 and Magic Mountain Pkwy. | Full Notice 


Gavin Canyon Undercrossing bridge foundation and utility work along the northbound shoulder, between Calgrove Bl and Weldon Canyon Rd. | Full Notice 


Butte Canyon bridge concrete pouring in the center median between Pico Canyon Rd/Lyons Av and McBean Pkwy, adjacent to Vista Valencia Golf Course. | Full Notice 

Magic Mountain Pkwy to Parker Rd  

Full or partial lane closures of Rye Canyon Rd between The Old Road and Avenue Stanford. View the full construction notice for the schedule and detour routes. | Full Notice 


Santa Clara Overhead Bridge excavation activity, located between Magic Mountain Pkwy and Rye Canyon Rd. | Full Notice 


Castaic Creek bridge demolition activity in the center median between SR-126 and Hasley Canyon Rd. | Full Notice  


Center median paving work between Magic Mountain Pkwy and SR-126. | Full Notice  


Center median concrete placement between Magic Mountain Pkwy and Parker Rd. | Full Notice  


Important Note 

Due to pile driving activity, smoke will be visible from the I-5 freeway and The Old Rd at the Gavin Canyon Rd Bridge work zone, located between Weldon Canyon Rd and Calgrove Bl. Pile driving at this location is anticipated to continue through Summer 2023. If you have any questions regarding the active construction smoke, please call or email the I-5 NCEP hotline. 

Essential Details    

  • Work hours: Monday through Friday and Saturday, as needed from 7am to 4pm and 7pm to 6am. Crews will begin to mobilize at 6am.    
  • No two consecutive ramps in the same direction will be closed at the same time. Detours to the next on-ramp will be posted for each closure.    
  • Traffic will be maintained in each direction.     
  • All lanes will reopen by 6am each morning.      
  • No lane closures will be implemented during morning or evening peak traffic hours.    
  • The speed limit in construction work zones is reduced to 55 miles per hour.    

Noteworthy    

Access to emergency responders will be maintained. Construction is a dynamic process, it is subject to weather conditions, and information is subject to change, visit the project website for the most up to date information and a weekly listing.  

 

  • Metro's Community Relations team has created a Frequently Asked Questions (FAQs) document that is now available to you as a resource. |  More Information
  • Our project team invites you to join our e-mailing list to get the latest details on upcoming construction. |  More Information
  • See all active construction notices for this project.| More Information